- Is PPAP the same process as a ISIR (Initial Sample inspection report)?
Early on, as I understand it, ISIR (also called ISR and several other acronymns) was just a layout inspection I first ran into ISIR (Initial Sample Inspection Report) requirements during the military manufacturing phase of my life What comprised an ISIR in the 1970's and 1980's was dependent upon the specific contract and the specific customer
- Is PPAP the same process as a ISIR (Initial Sample inspection report . . .
ISIR is a summary of the initial sample being presented at what ever state The PSW is supported and validated by the ISIR This does not mean the product being presented is under serial conditions but just states with evidence the current status PPAP is the confirmation that the product meets the customer requirements for series production
- ISIR (Initial Sample Inspection Report) vs. PSW (Part Sample Warrant)
ISIR vs PSW I have read articals (can't remember which publications, but have seen it twice) when refering to Initial Sample Inspection Report (ISIR) it was followed by (Now PSW)
- PPAP - Intent of an ISIR - The Elsmar Cove Quality Forum
Hello all, in our company there is a hot discussion going on We are wondering what is the intent of an ISIR in connection to get a PPAP approval We know an ISIR (like the name explains) is an INITIAL SAMPLE INSPECTION REPORT Now there are to different opinions in what way to submit
- How to report Basic Dimensions on a Dimensional Report (ISIR)
Re: How to report Basic Dimensions (ISIR) I would report a 10 mm basic (as an example) as 10 mm If the person reading the report does not understand, then they need to take a GD T course Basic dimensions are theoretical dimensions and the tolerances are shown in the feature control frames Sometimes basic dimensions define an area so, again, just state under "Actual" the basic dimension
- FAI (First Article Inspection) vs PPAP (Production Part Approval Process)
Hi Covers, I am having hard time understanding the difference between FAI and PPAP for a new supplier and an existing supplier Maybe these questions will help you understand the trouble I am facing: When is a PPAP performed and when a FAI? Are the both performed at Supplier Site or where are
- ISIR vs. PPAP - Customer is requesting an ISIR Cover Sheet according VDA
A customer is requesting an ISIR Cover Sheet according VDA for a small amount of pieces and promises a fix amount for the next several years I am the PPAP-responsible in my company and so here is the question Do i have to create a new PPAP for this type only because of the cover sheet according VDA?
- Ballooning a Print (Drawing) - A correct way to do a bubble print for . . .
Can anyone tell me if there is a correct way to do a "bubble" print for a PPAP - that is, the numbering sequence - clockwise, counter-clockwise
|
|
|