2018 | Paradigm Enterprises Paradigm provided all labor and material for foundation work, fencing, conduit, cable trench, control power cable and grounding We also provided labor for a complete installation and energization of all Wanzek and Xcel furnished substation equipment and bus work
2016 - Paradigm Enterprises Paradigm furnished all civil work from site subgrade development to finish rock We furnished and installed all foundations, fencing, grounding, conduits, cable trench and low voltage power control cable
2015 | Paradigm Enterprises Paradigm Enterprises 2015 Stephens Ranch Phase II North Collector Substation, O’Donnell, TX December 2014 – Present This 345 34 5kV – 235MVA wind farm collector substation is an ongoing project which will tie into the now existing SR I Substation